内容简介 《DL/T5181-2003 水电水利工程锚喷支护施工规范(英文版)》为英文版,主要内容有:Scope、Normative References、Terms and Definitions、General、Construction of Anchor Bars、General、Anchor Bar Bonded in Full Length、Tension Anchor Bar、Friction Anchor Bar、ubeAnchor Bar and Self-drilling Grouted Anchor Bar、Prestressed Tendon Construction等等。
编辑推荐 《DL/T5181-2003 水电水利工程锚喷支护施工规范(英文版)》由中华人民共和国国家经济贸易委员会发布。
目录
Foreword
1 Scope
2 Normative References
3 Terms and Definitions
4 General
5 Construction of Anchor Bars
5.1 General
5.2 Anchor Bar Bonded in Full Length
5.3 Tension Anchor Bar
5.4 Friction Anchor Bar
5.5 TubeAnchor Bar and Self-drilling Grouted Anchor Bar
6 Prestressed Tendon Construction
7 Shotcrete Construction
7.1 Raw Materials
7.2 Construction Equipment
7.3 Mix Proportion, Mixing and Delivery
7.4 Preparation Prior to Shotcreting
7.5 Shotcreting
7.6 Sand-enveloped-with-cement Shotcrete
7.7 Steel Fiber-reinforced Shotcrete
8 Anchor and Shotcrete Support
8.1 Wire Mesh-reinforced Shotcrete
8.2 Steel Arch Rib and Wire Mesh for Shotcrete
8.3 Anchor and Shotcrete Support under Adverse Geological Conditions
9 Safety Technologies and Dust Prevention
9.1 Safety Technologies
9.2 Dust Prevention
10 Quality Inspection
10.1 Anchor Bar and Tendon
10.2 Shotcrete
Appendix A (Normative Appendix) Methods for Monitoring and Survey of Anchor and Shotcrete Support
Appendix B (Informative Appendix) Testing Method for Grouting Compactness
Appendix C (Normative Appendix) Measurement Method for Dust Concentration in Shotcrete Working Area
Appendix D (Informative Appendix) Testing Method for Pullout Resistance of Anchor Bar
Appendix E (Normative Appendix) Testing Methods for Compressive Strength of Shotcrete
Appendix F (Normative Appendix) Testing Method for Anti-seepage Indexes of Shotcrete
Appendix G (Normative Appendix) Testing Method for Shotcrete Tensile Strength
Appendix H (Normative Appendix) Testing Method for Frost Resistance of Shotcrete
Appendix I (Normative Appendix) Testing Methods for Bond Strength of Shotcrete and Surrounding Rock
……
文摘 插图:

8 During grouting,if grout leakage occurs in inner anchoragesection due to breaking of grout stop ring,the tendon shall be pulledout SO as to flush away the grout in hole with clear water,replace thegrout stop ring,re-install the tendon and conduct grouting in the inneranchorage section.
6.0.6 Relevant regulations for tensioning and locking of tendon:
1 Test in-situ shall be conducted for tensioning of anchor barsSO as to determine reasonable tensioning techniques,to verify thetensioning parameters and tO avoid compulsory tensioning.
2 Before tensioning,tensioning equipment shall be calibrated.
3 Tendon tensioning shall be conducted according to specifiedprocedures.Tensioning procedure shall be designed by consideringthe mutual influence of adjacent tendons during tensioning.
4 Before the formal tensioning,pre-tensioning shall beconducted once or twice with single-tendon jack to keep each part intight contact and steel wire or steel strand straight.The pre-tensioningload may be 20%——30%of the designed tensioning load.
5 During the formal tensioning,tensioning and pressure。stabilizing shall be made according to the designed load increasing rangeand the stabilizing duration,and then locking shall be conducted.If theload increasing range and the duration of pressure stabilizing are notspecified in design,the tensioning load shall be increased tO 1 1 0%ofthe design one,and then the stabilizing pressure shall be kept at least2min before locking.
6 Within 48 h afterlocking,ifloss ofprestress is larger than 10%of the design load,compensation tensioning shall be made.