在10月24日要举行PMP第四次考试,离考试的时间越来越近,不知道考生有没有准备好,在这里编辑整理了一些PMP的练习题,希望能对考生有所帮助。也希望考生能顺利通过考试。 1 The Japanese Quality Control (QC) Circle movement motivated its participants in many ways. Which of the following represents the most important motivation for the QC circle participants?A improving the performance of the company
B self-improvement
C financial incentives
D recognition among co-workers
E strengthening of relationships between co-workers
ans:A
2 The Pareto Principle is a technique used by quality managers to determine which quality control problems of a particular service or manufacturing process should be corrected. Which of the following statements represents the philosophy of the principle?
A In order to minimize financial losses from quality control problems, all problems which have a measurable cost associated with them should be corrected.
B the majority of defects are caused by a small percentage of the identifiable problems. Improvements efforts should be reserved for these vital few problems.
C in order to achieve zero defects, all quality control problems, including those which do not have a direct financial cost should be corrected.
D generally, 80 % of the quality control problems are justifiable for correction via cost-benefit analysis. The remaining 20% are not financially worthy of improvement efforts.
E A and D 来源:考试大
ans:B
3 A process characteristic has a true mean of 150 and a true standard deviation of 20. A sample of 25 items is taken from this process. The standard error of the estimate is:
A 0.2
B 0.8
C 4
D 5
E 7.5
ans:C
4 Quality attributes
A are used to determine how effectively the organization accomplishes its goals
B can be objective or subjective in nature
C are specific quality characteristics for which a product is designed, built, and tested.
D A and B.
E B and C
ans:E
5 A proven effective means to insure quality conformance is to:
A delegate accountability to subordinates
B revise quality specifications to match quality measurements
C train workers in proper quality methods
D inspect quality into the product 来源:www.examda.com
E make quality a higher priority than cost or schedule
ans:C
6 What is the relative priority of project Cost, Schedule and Quality?
A 1)Cost - 2)Schedule - 3)Quality
B 1)Quality - 2)Schedule - 3)Cost
C 1)Quality - 2)Cost - 3)Schedule
D 1)Schedule - 2)Quality - 3)Cost
E All are of equal priority
ans:E
7 The quality objectives are approved in the conceptual stage of the project by the:
A Project Engineer
B Project Manager
C Functional Manager
D Quality Assurance Manager
E Project Owner
ans:E
8 Of the following, who has the ultimate responsibility for meeting project quality objectives?
A Project Engineer
B Project Manager
C Functional Manager
D Quality Assurance Manager
E Project Owner 来源:www.examda.com
ans:B
9 Utility Theory:
A considers the risk propensity of the decision makers.
B is based on proven statistical methods.
C deals with the usefulness of the end product.
D is a key element of ISO 9000
E B and C
ans:A
10 The Risk of NOT meeting project quality objectives:
A can be minimized through continuous monitoring.
B considered a long term risk.
C will be reflected in the "in-service" life of the product or service.
D B and C
E All of the above.
ans:E
11 The "zero defect" concept was proposed by:
A Deming
B Juran
C Crosby
D Tagushi
E A and D only
ans:C
12 The use of quality circles:
A has proven ineffective in both Japan and the U.S.
B is particularly effective in overcoming labor/management conflicts.
C provides a quick fix for most quality problems.
D allows workers the opportunity to generate solutions for chronic quality problems.
E A and B only
ans:D