  QUEST A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:

  A 4 weeks

  B 5 weeks

  C 6 weeks

  D 7 weeks

  E None of the above.

  B

  QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

  A All activities.

  B Only those activities with the longest time durations.

  C Those activities on the critical path begining with the longest time duration activities.

  D Those activities with the greatest degree of risk.

  E None of the above.

  C

  QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:

  A A shortening of the critical path.

  B A shortening of the noncritical path.

  C A decrease in the total cost of the project.

  D An increase in the cost of the project.

  E A through D are possible based upon where the resources are deployed.

  E

  QUEST Bar charts are most appropriate for:

  A Comparing actual to planned performance to each activity.

  B Showing slack time.

  C Showing critical path dependencies.

  D Showing which activities can be rearranged in parallel.

  E All of the above.

  A

  QUEST A non-critical path activity is completed in half the time. Then,

  A The critical path is also reduced.

  B The slack in the path containing this activity will increase.

  C The total cost for this activity has decreased.

  D Manpower from this activity can be assigned to other activities.

  E All of the above.

  B

  QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .

  A Slack for each activity, critical path.

  B Slack for each activity, high risk activities.

  C Manpower shortages, high risk activities.

  D High risk activities, non-critical paths.

  E Manpower availability, contingency plans.

  A

  QUEST ADM is an activity-on-arrow method. In this method, a dummy activity:

  A Denotes a critical path relationship.

  B Denotes any dependency relationship.

  C Shows slack.

  D Identifies customer deliverables dates.

  E Identifies customer team meeting dates.

  B

  QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ .

  A Project specification tree.

  B Customer's deliverable list.

  C Customer's milestone dates.

  D Work breakdown structure.

  E Listing of customer team meeting dates.

  D

  QUEST The critical path in a network is the path that:

  A Has the greatest degree of risk.

  B Will elongate the project if the activities on this path take longer than anticipated.

  C Must be completed before all other paths.

  D All of the above.

  E A and B only.

  B

  QUEST The major difference between PERT and CPM networks is:

  A PERT requires three time estimates whereas CPM requires one time estimate.

  B PERT is used for construction projects whereas CPM is used for R & D.

  C PERT addresses only time whereas CPM also includes cost and resource availability.

  D PERT requires computer solutions whereas CPM is a manual technique.

  E PERT is measured in days whereas CPM uses weeks or months.

  A

  QUEST A calendar that identifies when a project may be performed on an activity is called a:

  A Project calendar.

  B Resource calendar.

  C Milestone point.

  D Key point.

  E Work unit.

  A

  QUEST Planning activities such that predetermined resource availability pools are not exceeded is called:

  A Resource leveling.

  B Manpower leveling.

  C Resource limited planning.

  D Manpower planning.

  E Manpower contingency planning.

  C

  QUEST A comparison of completion status to baseline is referred to as _____.

  A Earned value measurement.

  B Percent complete.

  C ACWP.

  D BCWS

  E None of above.

  A

  QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:

  A Slack

  B Free float.

  C Restricted float.

  D Level float.

  E Lag

  E

  QUEST Overlapping activities on a project, such as design and construction, is referred to as:

  A Fast tracking

  B Risk conversion.

  C Parallel management.

  D Process improvement.

  E Synchronous manufacturing

  A

  QUEST A computer tape which contains historical project information is called ____ tape.

  A Database

  B Baseline.

  C Archive.

  D Lessons learned.

  E Life cycle summary.

  C

  QUEST Which method shown below is acceptable for reducing cost or shortening the schedule?

  A "Crashing"

  B Changing scope.

  C Performing activities in parallel rather than in series.

  D All of the above.

  E A and C only.

  D

  QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.

  A Increase, decrease.

  B Increase, increase

  C Increase, increase or decrease.

  D Decrease, decrease.

  E Decrease, increase.

  B

  QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.

  A Allocation.

  B Partitioning

  C Leveling

  D Quantification.

  E None of above.

  A

  QUEST Smoothing out resource requirements from period to period is called resource _____.

  A Allocation.

  B Partitioning

  C Leveling.

  D Quantification

  E None of above.

  C

  QUEST Guidelines for estimating time durations include:

  A Assuming a normal level of labor and equipment.

  B Assuming a normal work week.

  C Using consistent time units

  D Using past actual durations as guides.

  E All or part of each of the above.

  E

  QUEST Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?

  A PERT

  B ADM

  C PDM

  D All of the above.

  E A and C only.

  C

  QUEST In the PDM, common constraints include:

  A Start-to-start

  B Finish-to-start

  C Finish-to-finish

  D B and C only

  E A, B, and C.

  E

  QUEST Activities with zero time duration are referred to as:

  A Critical path activites.

  B Noncritical path activities.

  C Slack time activities.

  D Dummies

  E None of above.

  D

  QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources.

  A Events.

  B Activities

  C Slack elements.

  D B and C only.

  E All of the above.

  A

  QUEST On a precedence diagram, the arrow between two boxes is called:

  A An activity.

  B A constraint.

  C An event.

  D The critical path.

  E None of above.

  B

  QUEST A project element which lies between two events is called:

  A An activity.

  B A critical path method.

  C A slack milestone.

  D A timing slot.

  E A calendar completion point.

  A

  QUEST The basic terminology for networks includes:

  A Activities, events, manpower, skill levels and slack.

  B Activities, documentation, events, manpower and skill levels.

  C Slack, activities, events, and time estimates.

  D Time estimates, slack, sponsorship involvement, and activities.

  E Time estimates, slack time, report writing, life cycle phases, and crashing times.

  C

  QUEST The utility of network-based schedules:

  A Reveals interdependencies.

  B Facilitates "what if" exercises.

  C Highlights critical activities.

  D Provides information on resource requirements, time requirements and tradeoffs.

  E All of the above.

  E

  QUEST The major disadvantage of a bar chart is:

  A Lack of time-phasing.

  B Cannot be related to calendar dates.

  C does not show activity interrelationships.

  D Cannot be related to manpower planning.

  E Cannot be related to cost estimates.

  C

  QUEST The most common types of schedules are Gantt charts, milestone charts, line of balance, and:

  A Networks.

  B Time phased events.

  C Calendar integrated activities.

  D A and C only.

  E B and C only.

  A

  QUEST Scheduling is the process by which decisions are made concerning:

  A Tasks to be accomplished.

  B Personnel/organization that will be assigned to accomplish the task.

  C Time when the tasks are to be completed.

  D All of the above.

  E A and C only.

  E

  QUEST Time management is the allocation of time in a project's life cycle through the process of:

  A Planning

  B Estimating.

  C Scheduling.

  D Controlling

  E All of the above.

  E

  QUEST Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:

  A $19K

  B $21K

  C $26K

  D $29K

  E indeterminate

  C

  QUEST Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

  A Become worse, become worse

  B Become worse, improved

  C Improved, increased

  D Improved, become worse

  E None of the above are correct

  B

  QUEST The computation for Cost Performance Index is:

  A BCWP/ACWP

  B BCWP-ACWP

  C BCWP-BCWS

  D ACWP/BCWP

  E ACWP-BCWS

  A

  QUEST When comparing the cost of competing projects, which of the following is typically NOT considered?

  A Opportunity costs.

  B Direct costs.

  C Sunk costs.

  D Indirect costs.

  E Burden rates.

  C

  QUEST The Cost Performance Index (CPI) measures:

  A cost of work performed vs planned costs.

  B work performed vs cost of work performed.

  C work performed vs planned work.

  D direct costs vs indirect costs.

  E floating costs vs. sunk costs.

  B

  QUEST Parametric estimates are based on variables such as:

  A Detailed planning and cost restraints.

  B Physical characteristics and historical data.

  C The WBS and similar projects.

  D Project objectives and manpower allocations.

  E Precise measurements and multiple inputs.

  B

  QUEST Cost and schedule data are usually integrated because:

  A optimized project cash flow can affect financial requirements

  B they provide MIS with an integrated system to produce reports

  C they control escalation allowances

  D they account for omissions in the definitive estimate

  E they predict future performance

  E

  QUEST Continually measuring and monitoring the actual cost versus the budget is done to _____.

  A analyze the reasons for variances

  B establish the variances

  C identify the problems

  D All of the above.

  E None of the above.

  D

  QUEST Using the cumulative cost curve in the special window, height B represents

  A actual cost to date

  B total budgeted costs for the project

  C planned cost for month 6

  D cost variance

  E earned value

  B

  QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____.

  A establishing values for required functions

  B provide the required functions at the lowest overall cost.

  C identifies the required function of an item

  D seeks to trade performance for cost

  E None of the above.

  D

  QUEST The ability to achieve cost savings is inversely proportional to _____.

  A the earned value achieved to date

  B the estimated costs to complete

  C empowerment to the P.M.

  D productivity

  E None of the above.

  A